An electric hoist uses an electric motor to drive a load chain or wire rope, and it hangs from an overhead rail, a jib crane or a gantry crane. A plant needs one when loads heavier than about 25 kg are lifted many times per shift: molds, CNC workpieces, motors, drums, material rolls or crates.
A wrong choice usually shows up in three ways: the rated capacity is too close to the real load and the hoist wears out early, the speed is too fast so the load jerks and is hard to place on a fixture, or the hoist does not match the power supply on the shop floor. Below are the five steps the FullSharp engineering team uses during a site survey.
Capacity is the heaviest load plus the weight of the tool (hook, gripper or vacuum pad), plus a 20–25% margin. A 300 kg mold handled with a 40 kg gripper, for example, calls for a 500 kg hoist rather than a 350 kg one.
Power supply decides the series. Small workshops, garages or areas with only single-phase 220 V power suit a compact single-phase electric hoist rated 60–480 kg. Heavier loads and long daily running hours call for a three-phase 380 V hoist rated 125 kg to 20 tons, with an electromagnetic brake and IP55 dust and water protection.
Lifting speed affects both output and how safely a load can be set down. A two-speed hoist is enough for general lifting; a variable-frequency hoist runs fast with no load and lowers gently under load; a servo hoist is for positioning to the millimeter.
| Hoist type | Capacity | Lifting speed | Features | Best for |
|---|---|---|---|---|
| Single-phase electric hoist | 60–480 kg | Two-speed, fast and slow | 220 V supply, compact, easy to install and move | Assembly stations, shops without three-phase power |
| Three-phase electric hoist | 125 kg – 20 t | Two-speed, fast and slow | 380 V supply, electromagnetic brake, IP55, continuous duty | Machining, warehouses, long running hours |
| Hoist with adjustable slow lowering | 250 kg – 1 t | Two-speed, adjustable slow lowering | Brushless motor, cut-off on overload, overheating and abnormal voltage | Mold setting, assembly that needs fine alignment |
| Variable-frequency chain hoist | 125–5,000 kg | Stepless; half the usual low speed and up to 50% faster than the usual high speed | Soft start and stop, automatic slowdown near the upper limit | Lines that need fast lifting and soft lowering |
| Servo chain hoist | 125–5,000 kg | Stepless 0–16 m/min, down to 0.05 m/min | Dual brake, speed and fault code display, precise positioning | Precision assembly, molds, CNC loading |
| Clean room hoist | 125–2,000 kg | 1–12 m/min (light loads), 0.5–4 m/min (2 t) | Chain in a bellows dust cover, 380 V supply | Electronics, pharma, photovoltaics |
If operators have to guide the load into a bore by hand, also look at servo balancing hoists with float mode: the operator pushes lightly and the hoist follows the hand.
A hoist only performs well when it hangs from the right structure for the work area:
For lifting height, measure from the floor to the underside of the beam or rail, then subtract the height of the hoist, hook and tool. Low-ceiling plants should favor short-bodied chain hoists with aluminum housings.
Dusty or humid shops need IP55 protection or better. Clean rooms need a hoist with a bellows-covered chain and a housing that does not shed paint. Areas with solvents or paint, explosion risk, or a strict no-heat requirement should not use an electric hoist at all; use an air hoist or a pneumatic crane instead: no heat and no sparks.
Duty cycle matters too: a few lifts per hour is fine for a two-speed hoist, but continuous lifting all shift with cycles under a minute justifies a variable-frequency or servo hoist to cut jerking, brake wear and operator fatigue.
A single-phase 220 V hoist plugs into almost any workshop and suits loads of 60–480 kg. A three-phase 380 V hoist has a stronger motor and handles continuous duty better, from 125 kg to 20 tons, and is also available with variable-frequency or servo stepless speed control.
Inside a factory, for loads up to a few tons and moderate lifting heights, an electric chain hoist is compact, light and easy to hang from rails and jib cranes, so it is the common choice. Wire rope hoists suit large lifting heights or heavy double-girder cranes.
Take the heaviest load, add the weight of the tool (hook, gripper or vacuum pad), then add 20–25%. A 300 kg mold with a 40 kg gripper, for example, needs a 500 kg hoist.
When loads must be placed accurately on fixtures, into bores or onto CNC machines, when lifting runs continuously all shift, or when operators need float mode to guide the load by hand. A servo chain hoist offers stepless speed from 0 to 16 m/min, down to 0.05 m/min.
Yes. Electric hoists are lifting equipment and must be inspected before first use and at regular intervals as local regulations require; FullSharp provides the equipment documents at handover.
Send FullSharp the load weight (including the tool), lifting height, available power supply, preferred mounting type and photos of the work area for a free site survey and hoist recommendation.